Truck 1 quarters left to right in 1914, 1979, and 2004

Help Rescue Hook, Ladder & Bucket Company No. 1 Rebuild Their Firehouse

 
Home Page

R.H.& L. History

Thank You!

Contact Us

Donate On Line Online donation system by ClickandPledge

Click the "Click & Pledge" Icon  above to donate using your Visa &  Mastercard

Construction Progress

Last Updated on 09/17/2007

Scroll down to see progress of construction

October 2006, Pouring of the foundation & Footings

 

10/18/06 - Footings, and foundation complete. Wall block work begins.

10/19/06 North & South Wall Progress

10/25/06 Side and Back Walls on 1st floor complete, waiting for steel.

11-07-06

Most of the Structural Steel installed, 2nd floor decking C Channel on site.

11-30-06 More Block work on first floor complete, sub floor install begins

December 5th, 2006 2nd floor Wall construction progress

12-6-06 North Wall, 2nd fl. Progress

12/7/06 More 2nd Floor wall progress

12-16-06 Side Walls complete, front wall progress.

Below, overlay of computer model.

January 12, 2007 - Roof Truss Installation

Some of the trusses, including the one above arrived on the job site a bit short and some interior ceiling measurements were off. . Memo to the truss makers, measure twice and cut once.  The truss builders are working on a solution, meanwhile the job is on hold.
February 1st, 2007 Back to work!

A crew of truss workers arrived from Michigan and we begin again

2-11-07

2/16/07 - Despite the bitter cold temperatures, some modest progress is made with the repositioning of the south trusses and several of the front  gable trusses installed. ↑→

March, 2007

3/1/07 rear roof sheathed. Gray sided portion is existing structure from old firehouse.

3/1/07 Front view.

3/5/07 -2nd floor interior looking from back to front.

3/5/07 Preparations for gable block work.

3/10/07 Gable Block Work begins

Gable Block work finishing touches

3/10/07 toward front wall, 2nd fl.

3/12/07 Temporary window form removed, scaffolding removed, window sills installed. Work in progress over left entrance.

3/12/07

3/12/07

3/14/07 2nd fl walls sealed

4/21/07 Truck room floors poured, left & right windows installed

close-up of floors

ceiling grid for sheetrock

photos below of interior 1st & 2nd floor
May 7th, 2007

Bell tower framing complete

another view of bell tower

drywell installation

5/16/07 Progress Below

Brick columns between truck bays, stairs and railings, electric, heat and A/C work.

6-2-07

6/16/07

July 3rd, 2007 Soffit Trim amost complete

July 9th, 2007

Stucco Trimwork on windows completed. Preparations for concrete ramps underway.

Below 2nd floor sheetrock work almost completed.

7/12/07 Ramps Completed.

August 11th, 2008

Truck Room Sheetrock Taping

2nd floor looking towards rear show tile installation

Men's Room

Women's Room

View of tiled area

Rear Deck built off old structure

September 16th, 2007

Rear exit stairs for second floor

Front view, apparatus room doors will be replaced with white door shortly.

Second floor meeting hall painted and awaiting finished floors.

Apparatus room below - facing rear.

 

 
 

Hit Counter