October 2006,
Pouring of the foundation & Footings |
|
|
 |
|
10/18/06 -
Footings, and foundation complete. Wall block work begins. |
|
 |
 |
|
10/19/06 North & South Wall
Progress
|
 |
 |
|
 |
 |
|
↓10/25/06 Side and
Back Walls on 1st floor complete, waiting for steel. |
 |
 |
|
↓
11-07-06
↓
Most of the Structural Steel installed, 2nd floor decking C Channel on
site. |
 |
 |
|
|
11-30-06 More Block work on first
floor complete, sub floor install begins
 |
December 5th, 2006 2nd floor Wall
construction progress↓
 |
|
 |

12-6-06 North Wall, 2nd fl. Progress |
|

12/7/06 More 2nd Floor wall progress |

12-16-06 Side
Walls complete, front wall progress.
|
|
Below,
overlay of computer model. ↓

January 12, 2007
- Roof Truss Installation |
 |

 |
 |
 |

 |
 |
| Some of the trusses,
including the one above arrived on the job site a bit short and some
interior ceiling measurements were off. . Memo to the truss makers,
measure twice and cut once. The truss builders are working on a
solution, meanwhile the job is on hold. |
| ↓February 1st,
2007 Back to work! A crew of truss workers arrived
from Michigan and we begin again |
 |
 |
 |
 |
 |

2-11-07 |
|

2/16/07 - Despite the bitter cold temperatures, some
modest progress is made with the repositioning of the south trusses and
several of the front gable trusses installed.
↑→ |
 |
| March, 2007 |

3/1/07 rear roof sheathed. Gray sided
portion is existing structure from old firehouse. |

3/1/07 Front view. |
|

3/5/07 -2nd floor interior looking from back to front. |

3/5/07 Preparations for gable block work. |
|

3/10/07 Gable Block Work begins |

Gable Block work finishing touches |
|

3/10/07 toward front wall, 2nd fl. |

3/12/07 Temporary window form removed,
scaffolding removed, window sills installed. Work in progress over left
entrance. |
|

3/12/07 |

3/12/07 |

3/14/07 2nd fl walls sealed |

4/21/07 Truck room floors poured, left &
right windows installed |

close-up of floors |

ceiling grid for sheetrock |
|
photos below of interior 1st & 2nd floor |
 |
 |
 |
 |
 |
 |
|
May 7th, 2007↓ |
|

Bell tower framing complete |
|

another view of bell tower |

drywell installation |
 |
 |
 |
|
5/16/07
Progress Below ↓
Brick columns between truck
bays, stairs and railings, electric, heat and A/C work. |
 |
 |
 |
 |
 |
 |
 |
 |
 |
|
6-2-07↓
 |
|
6/16/07↓
 |
|
July 3rd, 2007
Soffit Trim amost complete
 |
|
July 9th, 2007
Stucco
Trimwork on windows completed. Preparations for concrete ramps underway.
Below 2nd
floor sheetrock work almost completed.
 |
|
7/12/07 Ramps
Completed↓.
 |
 |
 |
 |
 |
 |
 |
|
August 11th, 2008
 |
|
Truck Room Sheetrock Taping
 |
|
2nd floor looking towards
rear show tile installation
 |
|
Men's Room
 |
Women's Room
 |
|
View of tiled area
 |
|
Rear Deck built off old
structure
 |
|
September 16th, 2007

Rear exit stairs for second floor |

Front view, apparatus room doors will be replaced with white door
shortly. |

Second floor meeting hall painted and awaiting finished floors.


|
|
Apparatus room below - facing rear.
 |
 |
|
|